AIA%2C%20Change%20Order%20002%2C%20Agsten%20Construction%2C%20Ripley%20Middle%20School%20Renovations.pdf

Document typecontract
Date2023-06-20
Source URLhttps://go.boarddocs.com/wv/jac/Board.nsf/files/D4SLVX587408/$file/AIA%2C%20Change%20Order%20002%2C%20Agsten%20Construction%2C%20Ripley%20Middle%20School%20Renovations.pdf
Entityjackson_county_schools (Jackson Co., WV)
Entity URLhttps://www.boe.jack.k12.wv.us/
Raw filenameAIA%2C%20Change%20Order%20002%2C%20Agsten%20Construction%2C%20Ripley%20Middle%20School%20Renovations.pdf
Stored filename2023-06-20-fadd9454ee0593aac12ade0101c3e17c-contract.txt

Parent document: May 2, 2024, Regular Session-05-02-2024.pdf

Text

“AIA Document G701 - 2017

Change Order

PROJECT: (Name and address) CONTRACT INFORMATION: CHANGE ORDER INFORMATION:
Ripley Middle Schoo! Renovations Contract For: General Construction Change Order Number: 002

Date: March 07, 2022 Date: June 20, 2023
OWNER: (Name and address) ARCHITECT: (Name and address) CONTRACTOR: (Name and address)
Jackson County Board of Education ZMM Architects & Engineers, Inc. Agsten Construction Co., Inc.
1 School Street 222 Lee Street West 1700 State Route 34
Rapley, WV 25271 Charleston, WV 25302 Hurricane, WV 25526

THE CONTRACT IS CHANGED AS FOLLOWS:

(Insert a detailed description of the change and, if applicable, attach or reference specific exhibits. Also include agreed upon adjustments
attributable to executed Construction Change Directives.)

Provide all labor, materials and equipment necessary to complete the following:
COP #2: Added Door Hardware $759.74

COP #5: New Pipe Bollards $2,475.65

COP #6: Transformer Pad ($534.08)

COP #7: Roof Drain $6,244.04

Total: $8,945.35

The original Contract Sum was $ 3,214,000.00
The net change by previously authorized Change Orders $ 28,716.63
The Contract Sum prior to this Change Order was $ 3,242,716.63
The Contract Sum will be increased by this Change Order in the amount of $ 8,945.35
The new Contract Sum including this Change Order will be $ 3,251,661.98

The Contract Time will be increased by Zero (0) days.
The new date of Substantial Completion will be Unchanged

NOTE: This Change Order does not include adjustments to the Contract Sum or Guaranteed Maximum Price, or the Contract
Time, that have been authorized by Construction Change Directive until the cost and time have been agreed upon by both the
Owner and Contractor, in which case a Change Order is executed to supersede the Construction Change Directive.

NOT VALID UNTIL SIGNED BY THE ARCHITECT, CONTRACTOR AND OWNER.

ZMM Architects & Engineers, Inc. Agsten Construction Co., Inc. Jackson County Board of Education
OWNER (Firm name)
SIGNATURE

Nathaniel Spencer

Project Manager Sam Hull, President

PRINTED NAME AND TITLE PRINTED NAME AND TITLE PRINTED NAME AND TITLE

6/20/2023 6/20/2023

DAE DATE DATE

a ee ee ee
AIA Document G701 ~ 2017. Copyright © 1979, 1987, 2000 , 2001 and 2017. All rights reserved. “The American institute of Architects," “American Institute of
Architects,” “AIA,” the AIA Logo, and “AIA Contract Documents” are trademarks of The American Institute of Architects. This document was produced at 14:43:26
ET on 06/20/2023 under Order No.2114340562 which expires on 07/09/2023, is not for resale, is licensed for one-time use only, and may only be used in
accordance with the AIA Contract Documents® Terms of Service. To report copyright violations, e-mail docinfo@aiacontracts.com.

User Notes: (3B8ADA3B)